India’s Intended Nationally Determined Contribution (INDC) aims to base 40% of the total installed power generation capacity on non-fossil fuel resources by 2030 with international support on technology transfer and financing

The Government of India has set a target of installing of installing 175 GW of renewable energy capacity by the year 2022, which includes 100 GW from solar, 60 GW from wind, 10 GW from bio-power and 5 GW from small hydropower.

Ajmer Phagi transmission scheme is for transmission of renewable generation at state of Rajasthan, India.
The contract works includes complete design (Primary, Secondary, Civil) and construction on site (civil, erection, testing & commissioning). The substations are existing substations. 3 nos of 765 kV bays to be constructed in Ajmer (PG) substation and 1 no. of 765 kV bay to be constructed in Phagi (RRVPN) substation.